Protect the pressure boundary and critical interfaces through a staged inspection plan.
Valve body casting inspection should reflect the component’s role in the complete valve. Material identity, wall integrity, machined interfaces and pressure-related acceptance are distinct requirements. A clean exterior or a dimensional report does not establish that every requirement has been met, especially where later machining exposes internal material.

Define the governing requirement
Identify the valve design basis, casting material specification and customer supplementary requirements. The responsible designer should establish the applicable service and acceptance conditions. A generic product description such as industrial valve body is not enough to determine every required test.
Mark the pressure boundary, sealing locations, flange interfaces and critical internal geometry. These features help the foundry plan feeding, core location and machining stock. Review any proposed design adjustment before tooling release if it affects the flow path or component rating.
Verify material and traceability
The material certificate should identify the specified grade, condition and required results, with a clear link to the casting heat. Keep this identity through cleaning, heat treatment and machining. If marking is removed, transfer it using a controlled method before traceability is lost.
Confirm what documentation is required for any permitted repair. Customer or code requirements may restrict repair or impose additional processing and examination. Resolve these conditions before samples are cast rather than making an acceptance decision after a defect is discovered.
Inspect in the appropriate sequence
Raw casting examination can identify relevant surface or internal conditions before costly machining. Later inspection checks the features and material exposed by machining. The correct sequence depends on the part and specification, and should be defined in the inspection plan.
Where a pressure or leak test is required, specify the medium, stage, procedure and acceptance basis through the governing requirements. It is a separate activity from NDT and dimensional inspection. Avoid treating one result as a substitute for every other integrity check.
Build an inspection matrix
| Stage | Main question | Record |
|---|---|---|
| Material release | Is the intended grade and condition traceable? | Certificate and heat identification |
| Casting release | Do critical regions meet agreed integrity criteria? | Specified examination reports |
| Final component | Do interfaces and required tests conform? | Dimensional and applicable functional results |
Close deviations before repeat orders
Record every sample deviation and its disposition. An approved concession should identify the affected requirement and scope; it should not become an informal permanent change. Update the drawing or process only through the appropriate approval route.
Retain the accepted sample baseline and inspection plan for repeat production. A change to the core, pattern, feeding method or production location may require review. This keeps later bodies interchangeable and conforming instead of relying on a successful first sample indefinitely.
Frequently asked questions
Is a hydrostatic test the same as radiographic examination?
No. They evaluate different aspects of the component and neither automatically replaces the other.
Can a foundry choose the valve’s pressure rating from the alloy?
No. Rating follows the complete design and applicable rules, not the material name alone.
Discuss your component requirements
For related information, review general valve casting guidance, or define a valve-body inspection plan. Include the drawing revision, alloy, quantities and critical acceptance requirements so the proposed route can be reviewed against the actual part.
By Coco